A tender (or bid) is a submission made by a prospective supplier (such as a contractor) in response to an invitation to tender (ITT) from a client. It makes an offer for the supply of goods or services.
If a prospective contractor or supplier submits a tender which meets the client's stipulated requirements, (ie the mandatory elements of the Invitation to Tender (ITT) have been satisfied) then that bidder is said to have submitted a compliant bid.
Guidance to prospective bidders is usually clear about the requirements, in terms of precise information required, word length, presentation format, requirement for images, etc. Simply put, full compliance means all material conditions of a tender must be complied with and the price submitted should be based on the client’s tender specification documents.
If a tender is not compliant it may be rejected.
The precise content of a tender will vary considerably, depending on the procurement route, however it might include:
- A tender return slip, with details of the contract, including information such as return address and tender checklist;
- A completed tender pricing document (or contract sum analysis on design and build projects);
- Schedules of rates;
- An initial construction phase plan;
- Any design proposals or method statements that have been requested;
- Programme;
- Procedures to be adopted, such as procurement procedures and cost management procedures;
- Demonstration of capability, for example design capability, systems used etc;
- A BIM execution plan - if building information modelling is being used;
- Key project personnel, which may require submission of CVs;
- Management organisation;
- Plant and labour resources and availability;
- Prior experience, and
- References
However, some circumstances may allow a tender to be accepted even if it does not comply. A non-compliant proposal, sometimes referred to as a variant bid, may be submitted if the tenderer believes that an alternative could offer better value for money. However, non-compliant proposals should only be submitted if they have been requested or are explicitly permitted by the client, and they may need to be accompanied by a compliant bid.
[edit] Ways to create a compliant tender:
- Answer the question i.e. state what is required under each question;
- Answer all the question(s);
- Do not exceed the required word length;
- Do not supply information that is not required, e.g if a tender requires brief personal profiles, do not submit full CVs unless these are explicitly asked for;
- Do not leave sections blank;
- Submit in the correct format, e.g PDF, Excel, Word etc where required;
- Submit on time, and to the correct person;
- Ensure that proposals satisfy the client's requirements.
- Ensure works are packaged in the way the client requires.
- Visit the site, and if permitted, ask questions to avoid misunderstandings.
- Provide pricing information in the format and breakdown requested.
See also: Common mistakes in construction tenders.
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Bidder.
- Bid writer.
- Competitive tender.
- Contract award.
- Contract conditions.
- Contract documents.
- Due diligence when selecting contractors or subcontractors.
- Invitation to tender.
- Letter of award.
- Mid-tender interview.
- Most Economically Advantageous Tender (MEAT).
- Pre-tender interview.
- Procurement route.
- Selection criteria.
- Tender documentation.
- Tender evaluation.
- Tender processes.
Featured articles and news
New Great British Energy partnership launched
Crown estate help to turbocharge energy independence.
ECA Industry Awards 2024 shortlist revealed
22 leading businesses from across the electrotechnical and engineering services sector.
Government unveils Skills England strategy
Skills England to transform opportunities and drive growth.
New Government Hub for York Given Planning Green Light
For up to 2,600 civil servants, due for completion by 2028.
Construction Skills Certification Scheme cards
July update on Professionally Qualified and Academically Qualified Person Cards.
BSRIA Briefing 2024, November 22
Sustainable Futures: Redefining Retrofit for Net Zero Living.
The CLC on driving competency in the retrofit sector
Previously published roadmap on skills for net zero.
The first labour government King's speech in fifteen years
Construction industry reactions, support and some concern.
CIOB Retrofit of Buildings Technical Information Sheet
What retrofit is, the approach to be taken and processes to be followed.
Adapting Historic Buildings for Energy and Carbon Efficiency
Historic England advice note 18, free download published.
10 retrofit projects revisited 10 years after completion.
Information orders, building liability orders and SPVs
Key BSA terms and how they impact special purpose vehicles.
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.